Author Archives: admin

Asbestos Abatement Notice for Waterman Bldg. Rooms 308, 309, 309A, 310, 311, 311A, 312, 312A

ASBESTOS ABATEMENT NOTICE

BUILDINGS AND AREAS AFFECTED:
Waterman Building, Rooms 308, 309, 309A, 310, 311, 311A, 312, 312A

WHAT IS HAPPENING?
To facilitate renovations, Environmental Hazards Management Inc. will remove 1,113 square feet of carpeting, vinyl asbestos floor tile, and associated mastic. 156 square feet of sheetrock will also be removed leading into room 112A.

DURATION OF WORK:
Start Date:                 Monday, July 17, 2017
Completion Date:      Friday, July 28, 2017
Hours:                       6:00am-4:30pm

WHAT TO EXPECT:
A containment area under negative pressure will be constructed for the removal process.  During abatement, workers will wear personal and respiratory protection.  The containment area will be clearly marked and should not be entered unless a situation posing an Immediate Danger to Life and Health (IDLH) occurs, and if possible, this entry should be made with personal and respiratory protection.

There may be slight noise disturbance.

CONTACT NUMBERS:
Physical Plant, Training & Compliance Office           Phone: (802)656-7233
Physical Plant, Service Operations Support            Phone: (802)656-2560

 

Encampment Cleanup Notice for Centennial Woods

Encampment Cleanup Notice

Buildings and Areas Affected:
Centennial Woods near Sheraton Parking Lot

What Is Happening?
GW Savage will be dismantling and cleaning up debris from an encampment off of the Sheraton parking lot in the Centennial Woods.

Duration Of Work:
Start Date:                Tuesday, April 25, 2017
Completion Date:      Tuesday, April 25, 2017
Hours:                        9:00am-3:30pm

What To Expect:
During the cleanup operation GW Savage personnel will wear appropriate personal protective equipment.  All debris will be bagged and brought off site.  The makeshift structure will be dismantled and removed.  A general trash pickup of the area will also be conducted.

Contact Numbers:

Physical Plant, Training & Compliance Office           Phone: (802) 656-7233
Physical Plant, Service Operations Support             Phone: (802) 656-2560

 

 

Asbestos Abatement Notice for Votey Hall, Various Areas

ASBESTOS ABATEMENT NOTICE

BUILDINGS AND AREAS AFFECTED:
Votey Hall. Various Areas

WHAT IS HAPPENING?
Environmental Hazards Management Inc., will be conducting various abatement activities in several areas of the building to support the renovation relating to the S.T.E.M. project.

DURATION OF WORK:
Start Date:                  Wednesday, April 5, 2017
Completion Date:        Thursday, June 30, 2017
Hours:                          6:00am-4:30pm

WHAT TO EXPECT:
During abatement activities, a containment area under negative pressure will be constructed for the removal process.  During abatement, workers will wear personal and respiratory protection.  The containment area will be clearly marked and should not be entered unless a situation posing an Immediate Danger to Life and Health (IDLH) occurs, and if possible, this entry should be made with personal and respiratory protection.

There may be slight noise disturbance.

CONTACT NUMBERS:
Physical Plant, Training & Compliance Office              Phone: (802)656-7233
Physical Plant, Service Operations Support                Phone: (802)656-2560

 

Asbestos Abatement Notice for Votey Hall, Rooms 225, 225, 225B

ASBESTOS ABATEMENT NOTICE

BUILDINGS AND AREAS AFFECTED:
Votey Hall, Rooms 225, 225, 225B

WHAT IS HAPPENING?
Environmental Hazards Management Inc., will remove 1,157 sq. ft. of vinyl asbestos floor tile
and associated mastic from room 225, 225A & 225B. They will also remove two lab hoods and
lab top material.

DURATION OF WORK:
Start Date:               Monday, February 27, 2017
Completion Date:     Friday, March 17, 2017
Hours:                      6:00am-4:30pm

WHAT TO EXPECT:
A containment area under negative pressure will be constructed for the removal process. Paint
stabilization will also be performed inside this area. During abatement, workers will wear
personal and respiratory protection. The containment area will be clearly marked and should
not be entered unless a situation posing an Immediate Danger to Life and Health (IDLH)
occurs, and if possible, this entry should be made with personal and respiratory protection.
There may be slight noise disturbance.

CONTACT NUMBERS:
Physical Plant, Training & Compliance Office Phone:   (802)656-7233
Physical Plant, Service Operations Support Phone:     (802)656-2560

Asbestos Abatement Notice for Votey Hall, Boiler Room 001

 

ASBESTOS ABATEMENT NOTICE

BUILDINGS AND AREAS AFFECTED:
Votey Hal, Boiler Room 001

WHAT IS HAPPENING?
Environmental Hazards Management will remove 60.square feet of boiler materials on the small red boiler.

DURATION OF WORK:
Start Date:                 Wednesday, February 1, 2017
Completion Date:      Thursday, February 2, 2017
Hours:                        6:30am-4:00pm

WHAT TO EXPECT:

A containment area under negative pressure will be constructed for the removal process.  During abatement, workers will wear personal and respiratory protection.

The containment area will be clearly marked and should not be entered unless a situation posing an Immediate Danger to Life and Health (IDLH) occurs, and if possible, this entry should be made with personal and respiratory protection.

There may be slight noise disturbance.

CONTACT NUMBERS:

Physical Plant, Training & Compliance Office           Phone: (802)656-7233
Physical Plant, Service Operations Support             Phone: (802)656-2560

 

Asbestos Abatement Notice for Given Building, 4th Floor and 3rd Floor

ASBESTOS ABATEMENT NOTICE


BUILDINGS AND AREAS AFFECTED:
Given Building, 4th Floor and 3rd Floor.
Rooms C413A, C415A, C415, C419, C421, C421A, C423, C423A and C425.
Room C312A, C340, C340A, C344, C344A and C348.

WHAT IS HAPPENING?

NRC Inc. will remove 3244 (sqft) square feet of VAT and Mastic, 222 sqft of Carpet Adhesive, 460 sqft of Lab Counter Tops and Adhesive, 5 Lab Hoods, 18 sqft of Adhesive with Soapstone Sinks, 7 Peg Boards with Adhesive, 1 Lab Sink and 53 linear feet of TSI.

DURATION OF WORK: 4th Floor

Start Date:                 Monday, December 05, 2016
Completion Date:       Friday, December 16, 2016
Hours:                        6:30am-4:00pm

DURATION OF WORK:  3rd Floor

Start Date:                 Monday, December 19, 2016
Completion Date:       Friday, December 30, 2016
Hours:                        6:30am-4:00pm

WHAT TO EXPECT:

A containment area under negative pressure will be constructed for the removal process.  During abatement, workers will wear personal and respiratory protection.  The containment area will be clearly marked and should not be entered unless a situation posing an Immediate Danger to Life and Health (IDLH) occurs, and if possible, this entry should be made with personal and respiratory protection.

CONTACT NUMBERS:

Physical Plant, Training & Compliance Office           Phone: (802)656-7233
Physical Plant, Service Operations Support                Phone: (802)656-2560

Asbestos Abatement Notice for Votey Hall, Room 339

ASBESTOS ABATEMENT NOTICE

BUILDINGS AND AREAS AFFECTED:
Votey Hall,  Room 339

WHAT IS HAPPENING?
To accommodate renovations, staff from Training & Compliance Office will remove 90 square feet of vinyl asbestos floor tile and associated adhesive.

DURATION OF WORK:
Start Date:                Friday, September 16, 2016
Completion Date:     Tuesday, September 20, 2016
Hours:                       7:00am- 3:30pm

WHAT TO EXPECT:
During abatement, workers will wear personal and respiratory protection.  The abatement area will be clearly marked with yellow “Caution, Do Not Enter” tape as well as this notice. The work area should not be entered unless a situation posing an Immediate Danger to Life and Health (IDLH) occurs, and if possible, this entry should be made with personal and respiratory protection.

Expect noise consistent with light construction

CONTACT NUMBERS:

Physical Plant, Training & Compliance Office           Phone: (802) 656-7233
Physical Plant, Service Operations Support             Phone: (802) 656-2560

Guano Cleaning Notice for Billings Library, Tower associated with Room B501A

GUANO CLEANING NOTICE


BUILDINGS AND AREAS AFFECTED:
Billings Library, Tower associated with Room B501A

WHAT IS HAPPENING?
Environmental Hazards Management will be cleaning the clock tower of guano and securing netting
to keep birds out.

DURATION OF WORK:
Start Date:               Tuesday, July 5, 2016
Completion Date:     Friday, July 8, 2016
Hours:  6:00am – 4:30pm

WHAT TO EXPECT:
During cleaning activities, workers will wear personal and respiratory protection. The regulated
area will be clearly marked and should not be entered unless a situation posing an Immediate
Danger  to  Life  and  Health  (IDLH)  occurs,  and  if  possible,  this  entry  should  be  made  with
personal and respiratory protection.

CONTACT NUMBERS:
Physical Plant, Training & Compliance Office            Phone: (802) 656-7233
Physical Plant, Service Operations Support              Phone: (802) 656-2560

Guano Cleaning Notice for Ira Allen Chapel, Clock Tower

GUANO CLEANING NOTICE


BUILDINGS AND AREAS AFFECTED:

Ira Allen Chapel, Clock Tower

WHAT IS HAPPENING?
Environmental Hazards Management will be cleaning the clock tower of guano and dead birds.

DURATION OF WORK:
Start Date:               Tuesday, July 5, 2016
Completion Date:     Friday, July 8, 2016
Hours: 6:00am – 4:30pm

WHAT TO EXPECT:
During cleaning activities, workers will wear personal and respiratory protection. The regulated
area will be clearly marked and should not be entered unless a situation posing an Immediate
Danger to Life and Health (IDLH) occurs, and if possible, this entry should be made with
personal and respiratory protection.

CONTACT NUMBERS:
Physical Plant, Training & Compliance Office Phone:    (802) 656-7233
Physical Plant, Service Operations Support Phone:      (802) 656-2560

Asbestos Abatement Notice for Marsh Life Science, Room 232

ASBESTOS ABATEMENT NOTICE

BUILDINGS AND AREAS AFFECTED:
Marsh Life Science, Room 232

WHAT IS HAPPENING?
In support of routine maintenance, the Physical Plant Training and Compliance Office will remove 4 mudded fittings = 2 Linear Feet of thermal system insulation above the drop ceiling in Room 232.

DURATION OF WORK:

Start Date:                 Monday, June 20, 2016
Completion Date:      Monday, June 20, 2016
Hours:                        6:30am- 10:00am

WHAT TO EXPECT:
The insulation will be removed within glove bags which create an air tight seal around the asbestos containing material and a high efficiency vacuum will be utilized to provide the glove bags with negative pressure. Workers will wear respirators and protective clothing as a precaution and air monitoring will be performed.  The work area will be demarcated with yellow barricade tape, and posted with an asbestos “Danger” sign as well as this notice during the activity.  Entry to this area should be limited to authorized personnel involved in the removal activity during this time.

CONTACT NUMBERS:
Physical Plant, Training & Compliance Office           Phone: (802)656-7233
Physical Plant, Service Operations Support             Phone: (802)656-2560